Our company was founded here in Hungary, based on our main customer's demand. City of Győr was selected, after wide research. The company was established with a capital of 700.000.000 HuF based on below split between the founders:

  • 70% Shin-Etsu Polymer Europe B.V, The Netherlands
  • 30% Shin-Etsu Polymer Co. Ltd., Japan

Milestones: 

    • 2003.10 company foundation,
    • 2003.12 start the building re-work activities on the rental place,
    • 2004.03 installation of machinery,
    • 2004.03 start of assembly processes,
    • 2004.04 start LT24 production mode,
    • 2004.04 start screen printing technology,
    • 2004.12 own building takeover and start setup activities,
    • 2005.04 move into the "new" buiding,
    • 2005.05 start laser engraving technology,
    • 2005.06 start UV coating technology,
    • 2005.07 introduction of 5S,
    • 2005.12 ISO 9001 certification,
    • 2006.01 introduction of SC (Soft Coat) technology beindítása,
    • 2006.12 ISO 9001 cycle1 SA1, ISO 14001 certification,
    • 2007.07 Introduction of RC (rubber contact) technology,
    • 2007.11 ISO 9001 cycle1 SA2, ISO 14001 cycle1 SA1,
    • 2008.07 ISO TS 16949 preparation audit,
    • 2008.08 ISO 9001 cycle2 cetrtification and ISO 14001 cycle1 SA2 postponed,
    • 2008.08 ISO TS 16949 cycle1 certification,
    • 2009.03 takeover and start Customer related functions,
    • 2009.10 ISO 9001 cycle2 and ISO 14001 cycle2 certification,
    • 2009.10 ISO TS 16949 cycle1 SA1,
    • 2010.01 HQ approval for own sales activity,
    • 2010.07 ISO 9001, ISO 14001 cycle1 SA2s,
    • 2010.07 ISO TS 16949 cycle1 SA2,
    • 2010.08 start investigations for implementing VC-Film (view control film) technology,
    • 2011.04 HQ approval for taking over of VC-Film technology,
    • 2011.05 ISO TS 16949 cyle2 certification,
    • 2011.06 Research for localization of raw material supplies for VC-Film technology,
    • 2011.07 start dokumentations for clean room reworks for VC-Film technology
    • 2011.08 Tender release to Új Széchenyi Terv,
    • 2011.09 Start preparations and actual works,
    • 2011.10 test production of VC-Film technology,
    • 2011.10 audit of HQ for releasing VC-Film technology for mass production,
    • 2011.11 ISO 9001, ISO 14001 cycle1 SA2,
    • 2012.02 Mass production release of VC-Film technology,
    • 2012.02 Successfull tender 
    • 2012.04 ISO TS 16949 cycle2 SA1,
    • 2012.06 Visit of Japanese business people,
    • 2012.10 ISO 9001, ISO 14001 cycle2 certification, 
    • 2013.05 ISO TS 16949 cycle2 SA2,
    • 2013.10 ISO 9001, ISO 14001 cycle2 SA1 
    • 2014.05 ISO TS 16949, ISO 9001 cycle3 certification,
    • 2014.06 HQ approval for implementing LIM (Liquid Injection Molding) technology,
    • 2014.08 Installation of bridge crane
    • 2014.10 ISO 14001 cycle2 SA2
    • 2014.11 Installation of LIM machine
    • 2015.05 ISO TS 16949 and ISO 9001 cycle3 SA1
    • 2015.08 Sampling with LIM tools
    • 2015.10 ISO 14001 cycle3 certification
    • 2015.12 Installation of the new, automated LIM machines, LIM tool acceptance run
    • 2015.12 HQ approval for implementing sales and processing of TC (Thermo Conductive) products/ technology
    • 2016.02 Installation of the new, automated LIM machine, LIM tool acceptance run
    • 2016.03 Start LIM mass production
    • 2016.05 ISO TS 16949 and ISO 9001 cycle3 SA2
    • 2016.06 Successful company audit based on "SMETA 4 Pillars" guideline
    • 2016.10 ISO 14001 cycle3 SA1
    • 2017.01 HQ approval, for implementing SG (Silicon Gasket) technology,
    • 2017.05 ISO TS 16949 and ISO 9001 cycle4 certification,

Our plans:

    • 2017.10 ISO 14001 cycle3 SA2
    • 2018.05 IATF 16949, ISO 9001:2015 cycle5 certification,
    • etc.

 

Activity area:

Manufacturing of silicon base parts -whereas they are keypads, inner switches or tubes -, is our main profile. 

Main business area:

Electronics.

Growing areas:

Electronics (white goods), automotive and others.  

Postal address:

 H-9027 Győr, Hungary, Berkenyefa sor 2/a

Location parameters: 

•Company is located in Győr's Industrial Park.

•Land area: 14.000 m²; Building net area: 3.600 m²

Production floor's area: 3.000 m²; Building expansion possibility: 800 m²